Tuesday, August 31, 2010
Sunday, August 29, 2010
WEEKEND UPDATE.........
Friday, August 27, 2010
Wednesday, August 25, 2010
LET THE FRAMING BEGIN....... AGAIN.........
After a brief issue with the building permit and a stop work order from the city, framing resumed today. The third wall is up framing the patio door off the dining area, windows in kitchen and bathroom. The roofing material and windows have been ordered, final decision on cedar siding made. Jaimi and Brett arrive tomorrow from Minnesota with coolers of sweet corn, a fishing trip is scheduled for the weekend to fill up the coolers for their return trip in 10 days. Hope to have another big fish picture, Seraphina stories and a 2nd story built by the next post.
Sunday, August 22, 2010
A PERFECT SATURDAY........
Thursday, August 19, 2010
LET THE FRAMING BEGIN...........
The lumber arrived on the barge and was delivered to the site on Wednesday. Pictures were taken early morning Thursday, at noon and then at the end of the day looking through what will be the back door. The weather semi cooperated with most of the heavy rains over night.
Now for a quick fishing trip over the weekend, can't wait to see how things will look when we get back on Sunday. Hope to have a huge halibut picture to post too!
Wednesday, August 18, 2010
A PERFECT DAY..........

Friday, August 13, 2010
ALMOST DONE...........

Site prep is now in the final stages. Concrete is scheduled to be poured on Monday the 15th. First picture shows the trenches being dug for the utility pipes. The second the plumbers installing the in-floor heating system. And the third at the end of the day with the heating system in place. Now for a building inspection and the cement trucks can roll. Weather forecast is for sunny and 70's, should be perfect.
The lot was a challenge as a building site which was anticipated, but until the digging began and the set backs marked it wasn't known exactly what we were dealing with. Without blasting the rock off and spending lots of $$ or bringing in tons of fill and spending lots of $$, the plans have been downsized for the house and parking pad with the shop.
So at this time the shop is on hold, the good news is there will be room to park and more importantly turn around. Fill will be brought in down near road side for a possible shop in the future. If that doesn't work a shop will be built with Scott (Shawn's twin who lives within walking distance) at his house.
Hope to have an exciting update on Monday, enjoy the weekend!