Monday, January 31, 2011

LET THE COUNTDOWN BEGIN........




To move in day and the Super Bowl. Tile work in the upstairs bathroom is ready for grout. Trim work, touch up paint, appliances, plumbing, electrical etc. there is still lots to be done. At the least we should be able to watch the game from the house as the Directv dish is in place.
Only 6 days to go!


Monday, January 24, 2011

GO PACK GO.........




After a long wait on Saturday and a game that was tense for way too long, half of the dream Super Bowl scenario is in place, now back to the house for the other half. The kitchen counter is done, appliances will be next. Tiling in the bathroom continues.

Thursday, January 20, 2011

COUNTER TOP & TILE...........




Counters are now being installed in the kitchen, appliances might be in place by the weekend.
The tile work has begun on the upstairs bathroom, river pebble tile is in place in the shower pan.
The shower door has been ordered the last official big decision to be made. Now just patiently waiting for kick off on Sunday......and you thought I was going to say till move in day.

Tuesday, January 18, 2011

IN THE FINAL STAGES..........



The kitchen has been transformed from lines on the concrete to cabinets and drawers that can be opened and closed. The countertop is being built and will be installed by the end of the week. The bathrooms have been prepped for the tile work to begin. Good thing all the decisions have been made as Shawn has Packer Fever and nothing else is on his mind these days. The final touches on the siding is also done the corner pieces.

Friday, January 14, 2011

QUICK UPDATE #2



Cabinets almost all in place, counter top has been measured and will be ready early next week. Doors and windows are being trimmed out. Siding installed around the garden window and being finished on the back side of the house. Next big job is the tile in the bathrooms. Countdown to Super Bowl Sunday is on for more than one reason.......GO PACK!

Tuesday, January 11, 2011

QUICK UPDATE.......



Great room staging area, tile has been delivered and the utility room floor installed. Will get more pictures at lunch today. Rumor has it the cabinets are being uncrated, flooring on the 2nd floor is almost done and some doors are in.

Thursday, January 6, 2011

BACK TO WORK........




With the holidays over there's lots of activity in the first week of the new year at the house. Cabinets being off loaded, wood flooring being laid, cabinets, doors and trim ready for installation. Just a few minor last minute decisions and Shawn's goal of being in by Super Bowl should be met.